Full Site Logistics for Data Centre
London
Main Contractor:
Confidential
Project location / address:
London (Confidential)
Project summary:
Decommissioning and strip-out of redundant fittings, fixtures, structures and services in existing building. Data hall fit-out including associated electrical, mechanical, life safety, civil structural and architectural works. Completion date: March 2023 Project Lead @ The Shore Group: Petro Petava
Our involvement:
Full Site Logistics package. Management team of Contracts Manager and Logistics Manager. Additional site team of 10 including security, traffic management, handyman, welfare, forklift driver, slinger and labourers.
Contract Value:
£365,000